PROGRESS

The project is now complete. Stage progress is detailed on the right.

The following meetings have been held:

  • 11th January 2007 - Inception Meeting - held at British Geological Survey
  • 6th February 2007 - 1st Quarterly Progress Meeting - held at SKDC Stamford
  • 9th May 2007 - 2nd Quarterly Progress Meeting - held at SKDC Stamford
  • 15th August 2007 - 3rd Quarterly Progress Meeting - held at SKDC Stamford
  • 14th November 2007 - 4th Quarterly Progress Meeting - held at SKDC Stamford
  • 13th Frebruary 2008 - 5th Quaterly Progress Meeting - held at British Geological Survey
  • 6th May 2008 - 6th Quaterly Pogress Meeting - held at British Geological Suvey
  • 13th August 2008 - 7th Quaterly Progress Meeting - held at British Geological Survey
  • 19th November 2008 - 8th Quarterly Progress Meeting - held at INTERKONSULT Bottesford
  • 28th January 2009 - Final Meeting - held at VHE Leeds
  • The complete progress chart is shown below:

    If you wish to find out more information, please click on the links on this page or Email us now. We will endeavour to respond as soon as we can.